Share

After Stage One of the Kidston Solar Project began generating its first revenue in November 2017, Genex is now focusing on Stage Two which will see 270MW of solar power integrated with the Kidston Pumped Storage Hydro Project. With the project including around three million PV panels, it will become the first integrated solar pumped hydro project in the world.

The project is located in north Queensland on the site of the historical Kidston Gold Mine and is valued at close to $1 billion.

Upon completion, the project will generate up to 783GWh of renewable energy each year and will have a total of more than 3.5 million solar panels.

Stage Two of the Kidston Renewable Energy Hub consists of a 250MW pumped storage hydro project and an integrated 270MW solar project.

The pumped storage hydro project will utilise two of the mining pits from the abandoned gold mine, which will make up the upper and lower reservoir, powered by the integrated solar farm.

During peak power demand periods, water will be released from the upper to the lower reservoir and will pass through reversible turbines.

During off peak periods, the water will be pumped back from the lower reservoir to the upper reservoir using electricity primarily generated from the 270MW solar farm.

The innovation of the project extends even further, with the integration of large-scale solar providing a world-first example of generating, storing and dispatching renewable energy on demand during peak periods.

Choosing the right site

The Kidston site is situated in one of the highest solar radiation zones in Australia and is utilising the abandoned gold mine for the pumped hydro system which has allowed for a significant reduction in construction costs and time.

The project benefits from extensive existing on-site infrastructure and materials, mitigating the need for significant capital expenditure which is normally associated with the building of a large-scale pumped storage hydroelectric generation scheme.

Genex also owns the pipeline linking the nearby Copperfield Dam to the project site which enables access to 4,650ML of water annually which can be used for supplementing the Kidston scheme in a prolonged drought, contributing to the ideal location for the project.

Finding the funding

One of the biggest challenges that Genex has faced in the development of the project is being able to secure enough capital.

Given the close to $1 billion in capital cost and the size of the company, raising sufficient funds has been the main challenge for Stage Two.

However, Genex aims to replicate the successful funding arrangements for the Stage One Solar Project by using a long-term offtake agreement to underpin the project financing, and using the strong government support for the project to facilitate potential concessional debt funding.

In support of renewable energy projects, the Australian Renewable Energy Agency (ARENA) provided $8.9 million in funding to support the construction of Stage One, and has recently awarded additional Federal Government funding of up to $5 million to assist the financial close process of Stage Two.

ARENA CEO, Ivor Frischknecht, said Stage Two of the Kidston hydro and solar project is an important step in achieving a secure and reliable grid, and increasing the value delivered by renewable energy.

“Kidston will be the only grid connected solar project located in Australia’s solar red zone, providing consistent strong sun throughout the year, and combining it with pumped hydro will provide Queensland access to an entirely renewable flexible energy option,” Mr Frischknecht said.

The Queensland State Government has continued to support the Kidston Renewable Energy Hub, designating it as ‘Critical Infrastructure’ to the state which allows Queensland’s independent Coordinator-General to fast-track approvals and development timelines.

Why integrated solar?

Unlike other forms of renewable energy, the integration of large-scale hydro storage with solar will allow the project to provide dispatchable, reliable renewable energy at peak demand.

Genex is able to reduce losses associated with importing electricity from the grid for the pumped storage scheme, as well as mitigating any risk associated with rising overnight electricity prices when pumped storage schemes are usually ‘recharging’.

By integrating the 270MW Stage Two solar project, Genex is able to store significant amounts of solar energy during the day and release it during the morning and evening peak periods through the hydro system for up to eight hours.

The pumped hydro energy storage capacity was initially estimated at 1,500MWh, but a study conducted with global engineering firm Mott MacDonald, found that with optimal use of the site’s existing infrastructure and design of its turbine technology it could provide up to 2000MWh of energy.

Current project status

In November last year, the Kidston Solar Stage One project generated its first revenue following successful transformer energisation.

Electricity generation will be ramped-up until full capacity has been reached, at which point the 20-year Revenue Support Deed with the Queensland State Government will be initiated.

Genex’s Managing Director, Michael Addison, said the project has now transitioned from being technically operational to commercially active.

“This ground-breaking milestone marks the first earnings for the project and for Genex as a company. This transition from a development company to generating operational cash flows will serve to strengthen our financial position as we seek to reach financial close for our Kidston Stage Two projects in 2018.”

Genex has recently announced the appointment of head EPC contractors for the projects with a McConnell Dowell joint venture as the preferred contractor for the hydro and UGL, who delivered Stage One of the project, as preferred contractor for the Stage Two solar installation.

The target milestone date for financial close is the third quarter of 2018, with solar operations to begin in the first quarter of 2020 and the hydro operations to begin in the second quarter of 2021.

Related articles
0 Comments

©2023 Energy Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?